PASUQUIN HIGH SCHOOL OF ILOCOS NORTE, INC. (FORMERLY PASUQUIN ACADEMY)

“BUILDING A DREAM”  PROJECT
 

S U M M A R Y   O F  

C O N S T R U C T I O N   E X P E N S E S

(Abridged Version, Interim)

NOTE - THIS PAGE IS NOT UP TO DATE

PASUQUIN HIGH SCHOOL OF ILOCOS NORTE, INC. (FORMERLY PASUQUIN ACADEMY)

“BUILDING A DREAM”  PROJECT

 

SUMMARY OF CONSTRUCTION EXPENSES

(Abridged Version, Interim)

 

PHASE 1 - DURATION : APR 1, 2022 – AUG 15, 2022

Project Delivery Method : Construction Management

 

  1. PROPERTY SURVEY

  2. PERMITS & FEES (professional fees - working drawings (donated, no cost); Construction Manager (donated, no cost); building permit

  3. GENERAL REQUIREMENTS (machines, tool accessories, fuel). Jackhammer used for demolition , cutoff machine, welding machine, and 1 cement mixer were free rental

  4. SITE PREPARATION (demolition & removals  - courtesy of PTA parents, no cost)

  5. EARTHWORK & CONCRETE (excavation, fill & backfill, formwork & falsework, reinforcing steel bars, soil & aggregate, cement)

  6. MASONRY (1000 pcs of the total number installed were donated)

  7. MISCELLANEOUS METALS (railing)

  8. THERMAL & MOISTURE PROTECTION

  9. DOORS & WINDOWS (wood doors and jambs, door hardware – donated, aluminum windows & grilles)

  10. FINISHES (Painting 2 rooms interior only, painting corridor railing; 2 rooms floor tiles. Note 3rd room tiles by school)

  11. SPECIALTIES (school signage)

  12. ELECTRICAL (conduit & fittings, wire and cable, outlets & boxes, panelboards, lighting, alarm system)

  13. LABOR

  14. SNACKS (TWICE DAILY, PROVIDED BY THE SCHOOL)

  15. LUNCH FOR PTA PARENTS (PROVIDED BY SCHOOL)

 

TOTAL CONSTRUCTION COST PHASE 1 – P2,169,125.00

PHASES 2 & 3 (EAST WING) - DURATION : DEC 14, 2023 – JUN 30, 2024

Project Delivery Method : Construction Management

 

  1. PERMITS & FEES (DENR for tree cutting, INEC)

  2. GENERAL REQUIREMENTS (Purchased cement mixer, jackhammer, cutoff machine; tool accessories, fuel).

  3. SITE PREPARATION (demolition & removals  - some work involved PTA parents at no cost)

  4. TREE CUTTING & REMOVALS

  5. EARTHWORK & CONCRETE (excavation, fill & backfill, formwork & falsework, reinforcing steel bars, soil & aggregate, cement). Note – 263 cement bags were donated.)

  6. MASONRY

  7. MISCELLANEOUS METALS (fire exit, railing)

  8. THERMAL & MOISTURE PROTECTION (stair roofing)

  9. DOORS & WINDOWS (wood doors and jambs, door hardware – donated, aluminum windows & grilles)

  10. PRIME PAINTING (classroom interiors)

  11. EAST FENCE & GATE (at Tandang Sora)

  12. PLUMBING (rainwater leaders)

  13. ELECTRICAL (conduit & fittings, wire and cable, outlets & boxes, panelboards, lighting, alarm system)

  14. LABOR

  15. SNACKS (TWICE DAILY)

  16. LUNCH FOR PTA PARENTS (during “Panagbuhos”, some food donated by parents)

 

TOTAL CONSTRUCTION COST, PH 2 & PH 3 (EAST WING) –  P3,569,792.25

 

PHASE 4 (BALANCE OF WORK) - DURATION : NOV 25, 2024 – FEB 21, 2025

Project Delivery Method : Construction Management

 

  1. DEMOLITION & REMOVALS

  2. EARTHWORK & CONCRETE

  3. ROOF DECK WALL FINISHING (3 bays, south side)

  4. ROOF DECK TERRACE WATERPROOFING

  5. FINISHING (classroom floor tiles, building painting interior and exterior, Ladies comfort room floor and wall tiles, stair finishing)

  6. FIRE EXIT

  7. FENCING & GATE (south side at Burgos St.)

  8. PLUMBING (septic tank, water tank, pressure tank, Ladies comfort room fixtures and accessories, roof deck drainage, piping)

  9. ELECTRICAL (miscellaneous)

  10. MISCELLANEOUS OUTLYING AREA IMPROVEMENTS

  11. LABOR 

  12. SNACKS (TWICE DAILY)

TOTAL CONSTRUCTION COST, PH 4  –  P627,228.00 (?)

PHASE 5 - DURATION : Nov 1, 2025 – Jan 30, 2026

Project Delivery Method : Construction Management

1. CERAMIC TILES on the ground and second floors, entrance lobby and on stairwell landings. Non-slip nosings on stair treads.

2. FINISH PAINTING of ground floor only classrooms, corridors, washrooms, entrance lobby and stairwell. Miscellaneous touch up. (Lump Sum Contract)

3. PREPAINTED METAL CLADDING to cover exposed wiring, cables, and a portion of the old roof along the entrance walkway. These unsightly elements were exposed by earlier demolition works to make way for the new building construction.

4. ENTRANCE WALKWAY.

5. LABOR

6. SNACKS (TWICE DAILY)

TOTAL CONSTRUCTION COST, PH 5  –  P783,469.20

PHASE 6 - THIRD FLOOR ROOFING - DURATION : APR 29, 2026 – JUL 15, 2026

Project Delivery Method : Labour Contract

1. METAL ROOFING - Construction of a metal roof for the existing concrete deck to provide a covered third floor. This involved the extension of existing concrete columns; provision of structural steel roof framing, prepainted sheet metal roofing, concrete block enclosure on three sides, aluminum windows, and painting of exterior face of concrete block enclosures. The exterior painting ensures that the overall aesthetics of the building on the exterior is maintained.

2. The interior of the roofed area is unfinished and without partitions. In the meantime, the area can be used as convocation hall, and even classrooms with makeshift partitions. 

3. LABOR

 

TOTAL CONSTRUCTION COST, PH 6  –  P1,277,139.21

 

GRAND TOTAL – P8,426,753.66 (INTERIM)